Bulletin – December 7, 2021
Kimber Higa, Manager, Government Relations & Committees
Partial Energization Requests Due to Material Shortages
Fortis Alberta recognizes the material shortages the Development Community is currently experiencing as a result of the pandemic, and as such will work with developers and their representatives to review partial energization requests for a limited period (up to 1 year or until material issues are deemed cleared). The Bulletin provided by FortisAlberta provides a new set of considerations that have been evaluated as acceptable alternatives to support industry and development during the shortage material time.
Full details are available here