From: Beverly Jarvis – Director of Policy, Projects & Government Relations

Date: June 24, 2022

Subject: Site Energization Accountabilities – Informational

Enmax Power has provided BILD with a bulletin to ensure understanding and alignment across industry, on certain accountabilities during site energization and where responsibilities fall upon relevant stakeholders.

ENMAX Power is not responsible for the labor, workmanship and material that falls under Part 1 of the Canadian Electrical Code. More specifically, ENMAX Power will not ensure the existence of the electrical panel and the proper termination of the wires into the panel prior to energization; this is the accountability of Electricians and City of Calgary Electrical inspectors.

This notification serves as a reminder current standard practices that are currently in place.

To view the full bulletin from ENMAX, click here.

If you have any questions about the site energization process,

please contact Nelson Duerksen at 403-689-0323 or nduerksen@enmax.com.