BILD Calgary Region Bulletin 2022 – 88
| From: | Mohamad Mohamad |
| Date: | March, 1, 2023 |
| Subject: | Internal Construction Permission Process Update – Effective March 6, 2023 |
The City of Calgary is updating their internal construction permission request process.
Effective March 6, 2023, permission requests will no longer be circulated to infrastructure strategists, and the circulation timeline for Utility Generalist (formerly called Development Engineering) has been reduced to three business days. This new process will reduce the overall timeline of the permission request process from 14 business days to 7 business days.