Hot Mix Asphalt Placing Temperature
No hot mix asphalt shall be dispatched to the field unless the temperature, as issued by Environment Canada, is rising and meets the following minimum temperature requirements:
- Lift thickness less than 50 mm, 7°C
- Life thickness greater than 50 mm and less than 70 mm, 4°C
- Lift thickness greater than 70 mm, 2°C
- No surface lift asphalt mix shall be placed regardless of temperature or thickness until the road surface is 5°C or higher.
Concrete Placement Seasonal Requirement
When the air temperature is at or below 5°C, or when there is a probability of the temperature falling below 5°C within 24 hours of placing as forecast by the nearest official meteorological office, cold weather requirements for concrete placement shall apply.